Tamil Nadu’s Water Resources Department (WRD) has been told to take stock of a large water transfer scheme in the state’s west before any second stage goes ahead. The Hindu reported on 27 November 2026 that the assessment follows a directive from the state government and covers the Athikkadavu-Avinashi Underground Water Pipeline Project, about two years after it began operating.
The project was commissioned in August 2024. According to The Hindu, it takes 1.5 tmc of water from downstream of the Kalingarayan Anicut and sends it through pipelines to fill 1,045 water bodies. Those are spread across three districts: 299 in Coimbatore, 357 in Tiruppur and 389 in Erode.
The paper gave the working figures for a season of plentiful river flow. About 1.5 tmcft is pumped at roughly 250 cusecs over nearly 70 days. The system relies on six pumping stations and more than 1,000 km of pipeline.
For readers used to Australian units, a tmc is a thousand million cubic feet. That is a very large volume, but it is delivered only when the river has water to spare, so the scheme depends on surplus flow rather than guaranteed supply.
The Hindu said water could be pumped through the pipeline only in June this year. It also noted that supply was maintained at the same time of year in 2025 because surplus water was available.
One result the report singled out came from Thoravalur. Last year farmers there were able to grow paddy again for the first time in 50 years, which the report put down to the scheme strengthening groundwater recharge. That is the practical logic of filling tanks and ponds: the stored water soaks down and lifts the water table around it, helping wells that farmers depend on.
Farmers in the three districts have increasingly asked for Phase II over the past two years. Their concern is the water bodies they say were left out of the first stage. Farmers’ associations made an initial estimate that 1,400 tanks and ponds would need to be added. The state government has acknowledged that Phase II matters, according to the report.
The WRD has also looked at whether water for the second phase could be drawn further downstream on the Bhavani river, The Hindu said.
The report raises doubts that explain why an assessment is being done first. Officials are reported to have been advised by technical specialists that the existing pumps do not generate enough pressure, even for the water bodies already connected in the first phase. Adding hundreds more outlets to a system that is already stretched would make that problem harder.
The Hindu also cited sources saying the first phase was originally planned for no more than 700 water bodies. About 350 tanks and ponds were reportedly added “due to political pressure.” That would help account for the final total of 1,045 and for the pressure concerns, since a system sized for one number of outlets is now serving a much larger one.
The story does not set out what the WRD review will measure, or when it will report. What it does establish is the order of events: the government wants evidence from the first phase before taking the second forward.
For farmers waiting on Phase II, the review means more delay but also a chance that the next stage is built on measured results. For the department, the main practical questions raised by the report are these:
Those are questions drawn from the facts in the report, not findings the WRD has announced. The scheme’s one clear success so far, the return of paddy at Thoravalur, shows the concept can work where water arrives. Whether it can be stretched to another 1,400 water bodies on the same infrastructure is what the assessment will have to answer.
Because pumping happens when the river is abundant, the number of days available is limited. Every additional water body competes for the same volume in the same period. Adding the 1,400 sites farmers’ groups have estimated would, on the figures reported, put substantial new demand on a system that officials are already told has pressure shortfalls. That is why the downstream draw on the Bhavani has been studied: a different intake point is one way to supply more without relying only on the present setup.
The Hindu’s report is a short one and leaves many details open, including costs and timelines. The core of it is simple. Two years of operation have produced a measurable benefit in at least one village, a long list of unserved tanks and ponds, and reported technical limits that the WRD now has to weigh.